RG Building Surveyors Pte Ltd specialises in project management of maintenance and repair works to commercial and residential buildings. For each project we conduct a site audit and prepare a report on the  proposed contract works, prepare detailed tender documents / drawings, obtain competitive tenders from reputable contractors, prepare a tender report, conduct interviews with prospective contractors, award the contract, monitor the works on site and administer the contract including certifying contractors claims, issuing contract instructions and certifying completion of works etc. All projects are tightly controlled and managed by our qualified staff.
 
Below are some of the projects that we have managed from inception to completion:

 

1

The Sterling Condominium

232 residential units.

Works completed (2013) - Repainting, replacement of sealants to windows & curtain walls, rewaterproofing of all common area flat roofs and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 2

Park East Condominium

211 residential units.

Works completed (2013) - Repainting, plaster repairs, waterproofing of façade ledges, repair of spalling concrete, replacement of doors, rapair of water leakage, roof waterproofing, retiling, installation of  flashings and miscellaneous repairs.


 3

The Berth By The Cove (Sentosa)

200 residential units.

Works completed (2013) - Repainting, epoxy floor coating to basement car park, cleaning and sealing of natural stone external wall cladding, installation of flashings and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.



 4

The Marbella

239 residential units.

Works completed (2012) - Repainting, replacement of doors, pebble wash pavement repairs, drain repairs, replacement of sealants, installation of flashings and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.



 5

Goldenhill Park Condominium

390 residential units.

Works completed (2012) - Repainting, waterproofing of roof ledges, cleaning and sealing of granite tiled feature walls and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.



 6

Maplewoods Condominium

697 residential units.

Works completed (2012) - Repainting, replacement of cladding boards and waterproofing of architectural cladding features, rewaterproofing of  pavilion roofs and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.



 7

Casablanca Condominium

478 residential units.

Works completed (2011) - Repainting, installation of flashings / cappings and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.


 9

Orion @ Paya Lebar

Flatted warehouse development with ancillary office and show rooms.

Works completed (2011) - Repainting, replacement of window frame sealant, provision of cladding sealant, epoxy floor coating, water leakage repairs, replacement of metal roofing, installation of flashings, installation of rain canopy and miscellaneous repairs.

 10

Caribbean At Keppel Bay

969 residential units.

Works completed (2011) - Repainting, driveway repairs, installation of flashings / cappings and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.


 11

Tanglin View Condominium

384 residential units.

Works completed (2010) - Repainting, plaster repairs, glass block repairs, rewaterproofing of all flat roofs, pebble wash repairs and miscellaneous repairs. 

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 12

Carissa Park Condominium

528 residential units.

Works completed (2010) - Repainting, plaster repairs, waterproofing of ledges, installation of flashings, rewaterproofing / resurfacing of tennis court, driveway repairs, pool deck repairs and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 13

Equatorial Apartments

61 residential units.

Works completed (2009) - Repainting, rewaterproofing of all flat roofs and miscellaneous repairs.


 14

Northvale Condominium

762 residential units.

Works completed (2009) – Rewaterproofing of all common area flat roofs.

 15

Queens Condominium

722 residenial units. 39 storeys in height.

Works completed (2009) - Repainting, waterproofing of ledges, installation of flashings, installation of fencing, resurfacing of basketball court and putting green, regrading of drains, tiling repairs and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.



 16

Singapore Godown

Industrial building.

Works completed (2008) - Repainting, repair of stainless steel cladding features, plaster repairs, rewaterproofing of gutters and replacement of sealant to granite cladding, stainless steel features and precast concrete cladding.

 17

Northvale Condominium

762 residential units.

Works completed (2008) - Repainting, plaster repairs, replacement of window frame sealants, concrete repairs, installation of flashings, rewaterproofing works, driveway repairs and repair of pebble wash pavements.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 18

Westmere Condominium

280 residential units.

Works completed (2008) - Repainting, rewaterproofing / resurfacing of tennis court, glass block repairs, replacement of doors, replacement of bin chute hoppers, rewaterproofing of clubhouse roof terrace, rebuilding of boundary wall and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 19

Rosevale Condominium

32 residential units.

Works completed (2007) - Repainting, replacement of window frame sealants, rewaterproofing of canopies and miscellaneous repairs.

 20

Eastvale Condominium

312 residential units.

Works completed (2007) - Repainting, resurfacing of jogging track and children’s playground and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 21

44 Pioneer Sector 2

Steel portal frame building of approximatley 7000 sq metres.

Works completed (2006) - Replacement of corroded metal roof sheets, application of rust preventative coating to roof sheets, replacement of corroded purlins and tie rods, repainting of all steelwork and realignment of gutters.

 22

Blossomvale Condominium

220 residential units.

Works completed (2006) - Repainting, pitched roof gutter repairs, welding of new rainwater downpipe brackets, repair of soffit boards, replacement of metal balustrades and miscellaneous repairs.

Full time resident technical officer by RG Building Surveyors Pte Ltd.

 23

Kew Green Condominium

101 town houses.

Works completed (2006) - Repainting, brick tile repairs, timber repairs and miscellaneous repairs.



 

RG Building Surveyors Pte Ltd
450 North Bridge Road  #06-01 Singapore 188732
T: +65 6835 9625  F: +65 6835 9624
E: enquiry@rgbuildingsurveyors.com
www.rgbuildingsurveyors.com